Project Updates: The Black Hart of St. Paul Patio

Construction is moving quickly over at The Black Hart of St. Paul and we are excited to share the progress.

Highlights from Week 1:

  • Footing formwork for the frost pad at the new door complete

  • Inspector signed off on the footings

  • 6’ construction fence up around the site for safety

Highlights from Week 2:

  • The new sidewalk from University to the new door opening is now 100% complete

  • Concrete footings for the trellis and Simpson post bases are now all in

  • As a result of grading plan adjustments, 6 trucks worth of fill were brought onto the site to fill low spots and create gentle cross-site sloped plane

  • Fill and grading is 75% complete and on track to be completed by EOD

 

Looking ahead to Week 3:

  • Scheduling concrete cutting sub to come in and cut new door opening in CMU

  • New door install (+ hardware, trim, sealant, flashing, etc…)

  • Trenching for underground electrical

  • Fencing

 